On Monday, August 17th the construction fence panels in front of Townhouse buildings 7 & 8 will be removed and replaced withorange mesh fence. Mesh fence will be left in place to protect newly installed landscaping at Townhouse buildings 7 & 8. The construction entrance will remain in the same location, but the fence panels go from Townhouse building 6 to the jersey barricades at the TVA entrance next to Townhouses.
On Monday, August 10th the construction fence panels will be removed along the TVA entrance next to Townhouses and Naniloa Loop and replaced with jersey barricades. See below for an example of a barricade.
Sidewalk at the TVA entrance next to Townhouses remains closed and sidewalk along Naniloa Loop closes on Monday the 10th of August.
Week of August 10th the construction fence panels around the drainage area will start to be removed and replaced with orange mesh fence. See below for an example of an orange mesh fence.
July 31, 2020 Progress
Curbings and Detention at Area A
1 of 7
Na Hale Kumu Area A: Aerial View
2 of 7
Landscape Curbing and Walkway Extension at Building 8
3 of 7
Planter Concrete at Building 7
4 of 7
Regrading at Detention Area
5 of 7
Footing Excavation at Area A
6 of 7
Cabinet Delivery at Building 4
7 of 7
Copper Rain Gutters are Complete
1
of
7
Curbings and Detention at Area A
1 of 7
Na Hale Kumu Area A: Aerial View
2 of 7
Landscape Curbing and Walkway Extension at Building 8
3 of 7
Planter Concrete at Building 7
4 of 7
Regrading at Detention Area
5 of 7
Footing Excavation at Area A
6 of 7
Cabinet Delivery at Building 4
7 of 7
Copper Rain Gutters are Complete
1
of
7
July 24, 2020 Progress
Curbings and Drainage Basin
1 of 5
Overall Site of Na Hale Kumu Area A
2 of 5
Landscape Pavers at Townhouse Building 11
3 of 5
Front Planter Landscape Planter Curbing at Townhouse Building 6
4 of 5
Front Planter Landscape Curbing at Townhouse Building 7
5 of 5
Drainage Basin behind Buildings 4 and 5
1
of
5
Curbings and Drainage Basin
1 of 5
Overall Site of Na Hale Kumu Area A
2 of 5
Landscape Pavers at Townhouse Building 11
3 of 5
Front Planter Landscape Planter Curbing at Townhouse Building 6
4 of 5
Front Planter Landscape Curbing at Townhouse Building 7
5 of 5
Drainage Basin behind Buildings 4 and 5
1
of
5
July 17, 2020 Progress
Area A: Outdoor Projects
1 of 5
New HECO Power Pole
2 of 5
Back Fence Line
3 of 5
Building 1: Kitchen
4 of 5
Back Yard at Building 4
5 of 5
Forming for Landscape Curbing at Building 6
1
of
5
Area A: Outdoor Projects
1 of 5
New HECO Power Pole
2 of 5
Back Fence Line
3 of 5
Building 1: Kitchen
4 of 5
Back Yard at Building 4
5 of 5
Forming for Landscape Curbing at Building 6
1
of
5
July 10, 2020 Progress
Na Hale Kumu Area A: Outdoor Work
1 of 8
Townhouse Concrete Wall Footing Excavation
2 of 8
Faculty Townhouse Fence Installation
3 of 8
Fencing between Faculty Townhouse Buildings
4 of 8
Basketball/Play Area Sidewalk Access at Faculty Townhouses
5 of 8
Faculty Townhouse Building 5
6 of 8
Water Heater Installation at Townhouse Building 7
7 of 8
The backyard of Townhouse Building 8
8 of 8
The Gap between the Vinyl Fence at Townhouse Building 8
1
of
8
Na Hale Kumu Area A: Outdoor Work
1 of 8
Townhouse Concrete Wall Footing Excavation
2 of 8
Faculty Townhouse Fence Installation
3 of 8
Fencing between Faculty Townhouse Buildings
4 of 8
Basketball/Play Area Sidewalk Access at Faculty Townhouses
5 of 8
Faculty Townhouse Building 5
6 of 8
Water Heater Installation at Townhouse Building 7
7 of 8
The backyard of Townhouse Building 8
8 of 8
The Gap between the Vinyl Fence at Townhouse Building 8
1
of
8
June 26, 2020 Progress
Kitchen Installation
1 of 3
Light Fixture Installation Ongoing
Building 6: Light Fixture Installation Ongoing
2 of 3
Pendant Light Fixture
Building 8: Pendant Light Fixture
3 of 3
Microwave Installation
Building 8: Microwave Installation
1
of
3
Kitchen Installation
1 of 3
Light Fixture Installation Ongoing
Building 6: Light Fixture Installation Ongoing
2 of 3
Pendant Light Fixture
Building 8: Pendant Light Fixture
3 of 3
Microwave Installation
Building 8: Microwave Installation
1
of
3
June 19, 2020 Progress
Installations in Area A
1 of 7
Overall Site of Area A
Overall Site of Area A Townhouses in Na Hale Kumu
2 of 7
Rain Gutter and Down Spout Installation
Building 3: Rain gutter and down spout installation on Building 3.
3 of 7
Drywall Hanging Complete
Building 4: Drywall hanging complete and taping starting.
4 of 7
Wall Closing Inspection
Building 5: Wall closing inspection
5 of 7
Cabinet Installation at the Kitchen
Building 6: Cabinet installation at the kitchen
6 of 7
Fridge Installation
Building 8: Fridge installation
7 of 7
Carpet Installation
Building 8: Carpet installation at level 2.
1
of
7
Installations in Area A
1 of 7
Overall Site of Area A
Overall Site of Area A Townhouses in Na Hale Kumu
2 of 7
Rain Gutter and Down Spout Installation
Building 3: Rain gutter and down spout installation on Building 3.
3 of 7
Drywall Hanging Complete
Building 4: Drywall hanging complete and taping starting.
4 of 7
Wall Closing Inspection
Building 5: Wall closing inspection
5 of 7
Cabinet Installation at the Kitchen
Building 6: Cabinet installation at the kitchen
6 of 7
Fridge Installation
Building 8: Fridge installation
7 of 7
Carpet Installation
Building 8: Carpet installation at level 2.
1
of
7
June 12, 2020 Progress
Na Hale Kumu Area A-Ongoing Progress
1 of 2
Insulation and Drywall Installation Ongoing in Townhouse #4
Insulation and drywall installation ongoing.
2 of 2
Wrapping Up Flooring
Building 8: Wrapping up flooring at Building 8.
1
of
2
Na Hale Kumu Area A-Ongoing Progress
1 of 2
Insulation and Drywall Installation Ongoing in Townhouse #4
Insulation and drywall installation ongoing.
2 of 2
Wrapping Up Flooring
Building 8: Wrapping up flooring at Building 8.
1
of
2
June 5, 2020 Progress
BYUH Townhouses 1-8
1 of 17
Aerial View of Na Hale Kumu/Townhouse Construction Site
Aerial View of Overall Site
2 of 17
Aerial Side View of Townhouses
Aerial Side View of Townhouses
3 of 17
Cabinet Shelving
Cabinet Shelving
4 of 17
Door Installation is Complete
Door installation is complete and carpentry installation is going.
5 of 17
Drywall Finishing is Going
Drywall finishing is going.
6 of 17
Gold Bond Drywall Installation
Gold bond drywall install at windows.
7 of 17
Drywall Installation has Started
Drywall installation has started.
8 of 17
Exterior Foam Installed
Exterior foam installed on top of tech shield sheathing.
9 of 17
Electrical Fixture Installation
The electrical fixture installation has started.
10 of 17
Building 6
Tile work is ongoing in building 6.
11 of 17
Gray Cabinets in the Kitchen.
Gray cabinets in the kitchen.
12 of 17
Laundry Room Gray Cabinets
Laundry room gray cabinets.
13 of 17
Gray Cabinets at Master Bath
Gray cabinets at master bath.
14 of 17
Modified Cabinet Layout
Modified cabinet layout due to the window placement at this unit. The washer is placed below the window and not next to the sink per the original design.
15 of 17
Modified Cabinet Layout 2
Modified cabinet layout due to the window placement at this unit. Corner cabinet was installed in lieu of wall cabinet and on the opposite sides open shelving was installed.
16 of 17
Open Shelf Cabinet
Open shelf cabinet at the sink.
17 of 17
The Countertop Installation
The countertop installation was completed this week.
1
of
17
BYUH Townhouses 1-8
1 of 17
Aerial View of Na Hale Kumu/Townhouse Construction Site
Aerial View of Overall Site
2 of 17
Aerial Side View of Townhouses
Aerial Side View of Townhouses
3 of 17
Cabinet Shelving
Cabinet Shelving
4 of 17
Door Installation is Complete
Door installation is complete and carpentry installation is going.
5 of 17
Drywall Finishing is Going
Drywall finishing is going.
6 of 17
Gold Bond Drywall Installation
Gold bond drywall install at windows.
7 of 17
Drywall Installation has Started
Drywall installation has started.
8 of 17
Exterior Foam Installed
Exterior foam installed on top of tech shield sheathing.
9 of 17
Electrical Fixture Installation
The electrical fixture installation has started.
10 of 17
Building 6
Tile work is ongoing in building 6.
11 of 17
Gray Cabinets in the Kitchen.
Gray cabinets in the kitchen.
12 of 17
Laundry Room Gray Cabinets
Laundry room gray cabinets.
13 of 17
Gray Cabinets at Master Bath
Gray cabinets at master bath.
14 of 17
Modified Cabinet Layout
Modified cabinet layout due to the window placement at this unit. The washer is placed below the window and not next to the sink per the original design.
15 of 17
Modified Cabinet Layout 2
Modified cabinet layout due to the window placement at this unit. Corner cabinet was installed in lieu of wall cabinet and on the opposite sides open shelving was installed.
16 of 17
Open Shelf Cabinet
Open shelf cabinet at the sink.
17 of 17
The Countertop Installation
The countertop installation was completed this week.
1
of
17
May 25, 2020 Progress
Interior Work
1 of 12
Screen Shot 2020-06-02 at 8.00.55 AM.png
2 of 12
Screen Shot 2020-06-02 at 8.02.26 AM.png
3 of 12
Screen Shot 2020-06-02 at 8.02.53 AM.png
4 of 12
Screen Shot 2020-06-02 at 8.04.01 AM.png
5 of 12
Screen Shot 2020-06-02 at 8.04.10 AM.png
6 of 12
Screen Shot 2020-06-02 at 8.04.43 AM.png
7 of 12
Screen Shot 2020-06-02 at 8.04.57 AM.png
8 of 12
Screen Shot 2020-06-02 at 8.05.35 AM.png
9 of 12
Screen Shot 2020-06-02 at 8.06.06 AM.png
10 of 12
Screen Shot 2020-06-02 at 8.06.22 AM.png
11 of 12
Screen Shot 2020-06-02 at 8.06.34 AM.png
12 of 12
Screen Shot 2020-06-02 at 8.07.17 AM.png
1
of
12
Interior Work
1 of 12
Screen Shot 2020-06-02 at 8.00.55 AM.png
2 of 12
Screen Shot 2020-06-02 at 8.02.26 AM.png
3 of 12
Screen Shot 2020-06-02 at 8.02.53 AM.png
4 of 12
Screen Shot 2020-06-02 at 8.04.01 AM.png
5 of 12
Screen Shot 2020-06-02 at 8.04.10 AM.png
6 of 12
Screen Shot 2020-06-02 at 8.04.43 AM.png
7 of 12
Screen Shot 2020-06-02 at 8.04.57 AM.png
8 of 12
Screen Shot 2020-06-02 at 8.05.35 AM.png
9 of 12
Screen Shot 2020-06-02 at 8.06.06 AM.png
10 of 12
Screen Shot 2020-06-02 at 8.06.22 AM.png
11 of 12
Screen Shot 2020-06-02 at 8.06.34 AM.png
12 of 12
Screen Shot 2020-06-02 at 8.07.17 AM.png
1
of
12
May 22, 2020 Progress
Area A-Interior and Exterior
1 of 19
Screen Shot 2020-05-26 at 3.12.23 PM.png
2 of 19
Screen Shot 2020-05-26 at 3.03.18 PM.png
3 of 19
Screen Shot 2020-05-26 at 3.03.39 PM.png
4 of 19
Screen Shot 2020-05-26 at 3.13.13 PM.png
5 of 19
Screen Shot 2020-05-26 at 3.13.22 PM.png
6 of 19
Screen Shot 2020-05-26 at 3.13.44 PM.png
7 of 19
Screen Shot 2020-05-26 at 3.14.01 PM.png
8 of 19
Screen Shot 2020-05-26 at 3.14.12 PM.png
9 of 19
Screen Shot 2020-05-26 at 3.14.35 PM.png
10 of 19
Screen Shot 2020-05-26 at 3.14.45 PM.png
11 of 19
Screen Shot 2020-05-26 at 3.14.56 PM.png
12 of 19
Screen Shot 2020-05-26 at 3.15.12 PM.png
13 of 19
Screen Shot 2020-05-26 at 3.15.20 PM.png
14 of 19
Screen Shot 2020-05-26 at 3.15.32 PM.png
15 of 19
Screen Shot 2020-05-26 at 3.15.55 PM.png
16 of 19
Screen Shot 2020-05-26 at 3.16.06 PM.png
17 of 19
Screen Shot 2020-05-26 at 3.16.27 PM.png
18 of 19
Screen Shot 2020-05-26 at 3.16.45 PM.png
19 of 19
Screen Shot 2020-05-26 at 3.17.07 PM.png
1
of
19
Area A-Interior and Exterior
1 of 19
Screen Shot 2020-05-26 at 3.12.23 PM.png
2 of 19
Screen Shot 2020-05-26 at 3.03.18 PM.png
3 of 19
Screen Shot 2020-05-26 at 3.03.39 PM.png
4 of 19
Screen Shot 2020-05-26 at 3.13.13 PM.png
5 of 19
Screen Shot 2020-05-26 at 3.13.22 PM.png
6 of 19
Screen Shot 2020-05-26 at 3.13.44 PM.png
7 of 19
Screen Shot 2020-05-26 at 3.14.01 PM.png
8 of 19
Screen Shot 2020-05-26 at 3.14.12 PM.png
9 of 19
Screen Shot 2020-05-26 at 3.14.35 PM.png
10 of 19
Screen Shot 2020-05-26 at 3.14.45 PM.png
11 of 19
Screen Shot 2020-05-26 at 3.14.56 PM.png
12 of 19
Screen Shot 2020-05-26 at 3.15.12 PM.png
13 of 19
Screen Shot 2020-05-26 at 3.15.20 PM.png
14 of 19
Screen Shot 2020-05-26 at 3.15.32 PM.png
15 of 19
Screen Shot 2020-05-26 at 3.15.55 PM.png
16 of 19
Screen Shot 2020-05-26 at 3.16.06 PM.png
17 of 19
Screen Shot 2020-05-26 at 3.16.27 PM.png
18 of 19
Screen Shot 2020-05-26 at 3.16.45 PM.png
19 of 19
Screen Shot 2020-05-26 at 3.17.07 PM.png
1
of
19
May 8, 2020
Interior Work of Area A
1 of 19
Screen Shot 2020-06-05 at 8.00.29 AM.png
2 of 19
Screen Shot 2020-06-05 at 8.01.03 AM.png
3 of 19
Screen Shot 2020-06-05 at 8.01.29 AM.png
4 of 19
Screen Shot 2020-06-05 at 8.01.48 AM.png
5 of 19
Screen Shot 2020-06-05 at 8.02.20 AM.png
6 of 19
Screen Shot 2020-06-05 at 8.02.37 AM.png
7 of 19
Screen Shot 2020-06-05 at 8.03.02 AM.png
8 of 19
Screen Shot 2020-06-05 at 8.03.16 AM.png
9 of 19
Screen Shot 2020-06-05 at 8.03.25 AM.png
10 of 19
Screen Shot 2020-06-05 at 8.03.40 AM.png
11 of 19
Screen Shot 2020-06-05 at 8.03.51 AM.png
12 of 19
Screen Shot 2020-06-05 at 8.04.07 AM.png
13 of 19
Screen Shot 2020-06-05 at 8.04.26 AM.png
14 of 19
Screen Shot 2020-06-05 at 8.04.49 AM.png
15 of 19
Screen Shot 2020-06-05 at 8.05.08 AM.png
16 of 19
Screen Shot 2020-06-05 at 8.05.25 AM.png
17 of 19
Screen Shot 2020-06-05 at 8.05.56 AM.png
18 of 19
Screen Shot 2020-06-05 at 8.06.20 AM.png
19 of 19
Screen Shot 2020-06-05 at 8.06.31 AM.png
1
of
19
Interior Work of Area A
1 of 19
Screen Shot 2020-06-05 at 8.00.29 AM.png
2 of 19
Screen Shot 2020-06-05 at 8.01.03 AM.png
3 of 19
Screen Shot 2020-06-05 at 8.01.29 AM.png
4 of 19
Screen Shot 2020-06-05 at 8.01.48 AM.png
5 of 19
Screen Shot 2020-06-05 at 8.02.20 AM.png
6 of 19
Screen Shot 2020-06-05 at 8.02.37 AM.png
7 of 19
Screen Shot 2020-06-05 at 8.03.02 AM.png
8 of 19
Screen Shot 2020-06-05 at 8.03.16 AM.png
9 of 19
Screen Shot 2020-06-05 at 8.03.25 AM.png
10 of 19
Screen Shot 2020-06-05 at 8.03.40 AM.png
11 of 19
Screen Shot 2020-06-05 at 8.03.51 AM.png
12 of 19
Screen Shot 2020-06-05 at 8.04.07 AM.png
13 of 19
Screen Shot 2020-06-05 at 8.04.26 AM.png
14 of 19
Screen Shot 2020-06-05 at 8.04.49 AM.png
15 of 19
Screen Shot 2020-06-05 at 8.05.08 AM.png
16 of 19
Screen Shot 2020-06-05 at 8.05.25 AM.png
17 of 19
Screen Shot 2020-06-05 at 8.05.56 AM.png
18 of 19
Screen Shot 2020-06-05 at 8.06.20 AM.png
19 of 19
Screen Shot 2020-06-05 at 8.06.31 AM.png
1
of
19
April 10, 2020 Progress
Na Hale Kumu Townhouses
1 of 4
Building 8 Aerial 1 04-10-2020.JPG
2 of 4
Building 1 Aerial 1 04-07-2020.JPG
3 of 4
Building 13 Aerial 1 04-10-2020.JPG
4 of 4
Area A Aerial 5.2 04-10-2020.JPG
1
of
4
Na Hale Kumu Townhouses
1 of 4
Building 8 Aerial 1 04-10-2020.JPG
2 of 4
Building 1 Aerial 1 04-07-2020.JPG
3 of 4
Building 13 Aerial 1 04-10-2020.JPG
4 of 4
Area A Aerial 5.2 04-10-2020.JPG
1
of
4
February 5, 2020 Progress
Okland Construction is in the finishing stages of demolition on the Na Hale Kumu Townhouses (NHK). The construction site is an active site with construction vehicles coming and going from the site throughout the day. The main access to the site for construction vehicles is the access road between NHK and the Temple View Apartments (TVA). For your safety, it is requested that pedestrians stay off the access road between NHK and TVA. Pedestrians can gain access to Naniloa Loop through the parking lot marked "TVA" as shown in the diagram below.
Important: The NHK construction site is an active Okland Construction project. Any and all access requires coordination with Okland Construction prior to entering the site.