

October 19, 2020 Update
Fitness Studio: Complete

1 of 4
Fitness Studio Interior Work is Complete

2 of 4
Fitness Studio is Complete
3 of 4
Fitness Equipment #1
4 of 4
Fitness Equipment #2
1
of
4
Fitness Studio: Complete

1 of 4
Fitness Studio Interior Work is Complete

2 of 4
Fitness Studio is Complete
3 of 4
Fitness Equipment #1
4 of 4
Fitness Equipment #2
1
of
4
September 28, 2020 Update
Storefront Install

1 of 2
Storefront Install

2 of 2
A Glass Door from the Inside and the Outside
1
of
2
Storefront Install

1 of 2
Storefront Install

2 of 2
A Glass Door from the Inside and the Outside
1
of
2
September 14, 2020 Update
Fitness Studio: Interior Work

1 of 2
Lighting and Fans Installed

2 of 2
Mirrors in Progress
1
of
2
Fitness Studio: Interior Work

1 of 2
Lighting and Fans Installed

2 of 2
Mirrors in Progress
1
of
2
July 20, 2020 Update


July 6, 2020 Update
Fitness Studio-Concrete Completed

1 of 3
Concrete and Trench Drain

2 of 3
Concrete Work is Complete

3 of 3
Soffit Demolition
1
of
3
Fitness Studio-Concrete Completed

1 of 3
Concrete and Trench Drain

2 of 3
Concrete Work is Complete

3 of 3
Soffit Demolition
1
of
3
June 29, 2020 Update
Concrete Placement

1 of 2
Concrete Placement #1

2 of 2
Concrete Placement #2
1
of
2
Concrete Placement

1 of 2
Concrete Placement #1

2 of 2
Concrete Placement #2
1
of
2
June 25, 2020 Update
Preparation for Pouring Concrete
1 of 4
Concrete Walk Way Extension
Concrete Walk Way Extension
2 of 4
The Concrete Walkway Extension
The Concrete Walkway Extension
3 of 4
Image Before Rebar Placement
Image Before Rebar Placement
4 of 4
Forms ready for pouring slabs at Racquetball Court area.
Metal and Wooden Forms for Pouring Slabs
1
of
4
Preparation for Pouring Concrete
1 of 4
Concrete Walk Way Extension
Concrete Walk Way Extension
2 of 4
The Concrete Walkway Extension
The Concrete Walkway Extension
3 of 4
Image Before Rebar Placement
Image Before Rebar Placement
4 of 4
Forms ready for pouring slabs at Racquetball Court area.
Metal and Wooden Forms for Pouring Slabs
1
of
4
June 8, 2020 Update
Rebar Placement

1 of 3
Concrete Forming

2 of 3
Trench Drain Excavation

3 of 3
Interior Electrical Demolition
1
of
3
Rebar Placement

1 of 3
Concrete Forming

2 of 3
Trench Drain Excavation

3 of 3
Interior Electrical Demolition
1
of
3
May 25, 2020 Update
Working on Walkway

1 of 3
Screen Shot 2020-06-02 at 9.02.04 AM.png

2 of 3
Screen Shot 2020-06-02 at 9.02.14 AM.png

3 of 3
Screen Shot 2020-06-02 at 9.02.25 AM.png
1
of
3
Working on Walkway

1 of 3
Screen Shot 2020-06-02 at 9.02.04 AM.png

2 of 3
Screen Shot 2020-06-02 at 9.02.14 AM.png

3 of 3
Screen Shot 2020-06-02 at 9.02.25 AM.png
1
of
3
The existing Weight Room is too small to serve the current campus community. In an attempt to provide additional fitness areas, the racquetball courts will be transformed into a new workout space. Two of the three courts will be remodeled to receive new fitness equipment and the third court will be transformed into a fitness classroom. Besides these internal changes, additional exterior space will also be created to meet student needs. The building will also receive necessary structural upgrades and new air conditioning.
April 2020 Update
Renovate Racquetball Building

1 of 3
Screen Shot 2020-05-07 at 3.24.35 PM.png

2 of 3
Screen Shot 2020-05-07 at 3.23.41 PM.png

3 of 3
Screen Shot 2020-05-07 at 3.24.14 PM.png
1
of
3
Renovate Racquetball Building

1 of 3
Screen Shot 2020-05-07 at 3.24.35 PM.png

2 of 3
Screen Shot 2020-05-07 at 3.23.41 PM.png

3 of 3
Screen Shot 2020-05-07 at 3.24.14 PM.png
1
of
3
March 2020 Update
Raquetball Renovation

1 of 2
Screen Shot 2020-04-13 at 2.24.10 PM.png

2 of 2
Screen Shot 2020-04-13 at 2.30.46 PM.png
1
of
2
Raquetball Renovation

1 of 2
Screen Shot 2020-04-13 at 2.24.10 PM.png

2 of 2
Screen Shot 2020-04-13 at 2.30.46 PM.png
1
of
2