Half of the Construction of CMU Walls at the Cafeteria
4 of 4
Half of the First Floor with CMU Walls
1
of
4
The Work of the Ground Floor
1 of 4
Cafeteria: Overall Site of the Ground Floor
2 of 4
The First Floor with CMU Walls
3 of 4
Half of the Construction of CMU Walls at the Cafeteria
4 of 4
Half of the First Floor with CMU Walls
1
of
4
Sidewalk Closure at McKay Gym
The sidewalk will be closed in front of McKay Gym on Tuesday, August 18 for 2 weeks in order for the contractor to install a waterline.
August 3, 2020 Update
CMU Wall Progress
1 of 5
CMU Wall Progress
2 of 5
CMU Wall Progress #2
3 of 5
CMU Wall Progress
4 of 5
Cafeteria Plumbing and Electrical Area B
5 of 5
Manhole Covers at Dock
1
of
5
CMU Wall Progress
1 of 5
CMU Wall Progress
2 of 5
CMU Wall Progress #2
3 of 5
CMU Wall Progress
4 of 5
Cafeteria Plumbing and Electrical Area B
5 of 5
Manhole Covers at Dock
1
of
5
July 27, 2020 Update
CMU Wall Construction
1 of 4
CMU Wall Construction
2 of 4
CMU Wall Construction #2
3 of 4
CMU Wall Construction
4 of 4
Plumbing Excavation
1
of
4
CMU Wall Construction
1 of 4
CMU Wall Construction
2 of 4
CMU Wall Construction #2
3 of 4
CMU Wall Construction
4 of 4
Plumbing Excavation
1
of
4
July 20, 2020 Update
The Foundation Work Progress
1 of 4
Overhead View
2 of 4
CMU Walls Started
3 of 4
Slab Preparation Area B
4 of 4
Storm Drain Manhole Installed
1
of
4
The Foundation Work Progress
1 of 4
Overhead View
2 of 4
CMU Walls Started
3 of 4
Slab Preparation Area B
4 of 4
Storm Drain Manhole Installed
1
of
4
July 6, 2020 Update
The Foundation Work of the New Cafeteria
1 of 4
The Foundation Work-New Cafeteria Site
2 of 4
Slab Preparation
3 of 4
Gas Line Excavation
4 of 4
Chilled Water Connection to Existing
1
of
4
The Foundation Work of the New Cafeteria
1 of 4
The Foundation Work-New Cafeteria Site
2 of 4
Slab Preparation
3 of 4
Gas Line Excavation
4 of 4
Chilled Water Connection to Existing
1
of
4
June 29, 2020 Update
The Cafeteria (CAF) Construction
1 of 6
Aerial View of New Cafeteria (CAF)
Aerial View of New Cafeteria (CAF)
2 of 6
Side View of New Cafeteria (CAF)
Side View of New Cafeteria (CAF)
3 of 6
Underground Plumbing
Underground Plumbing
4 of 6
Footings
Footings
5 of 6
Slab Electrical
Slab Electrical
6 of 6
Slab Vapor Barrier
Slab Vapor Barrier
1
of
6
The Cafeteria (CAF) Construction
1 of 6
Aerial View of New Cafeteria (CAF)
Aerial View of New Cafeteria (CAF)
2 of 6
Side View of New Cafeteria (CAF)
Side View of New Cafeteria (CAF)
3 of 6
Underground Plumbing
Underground Plumbing
4 of 6
Footings
Footings
5 of 6
Slab Electrical
Slab Electrical
6 of 6
Slab Vapor Barrier
Slab Vapor Barrier
1
of
6
June 8, 2020 Update
Foundation Work
1 of 7
New Cafeteria-Overall Site
2 of 7
Dock Sump Power and Pump Line
3 of 7
Electrical Slab Rough-In
4 of 7
Slab Edge Forming and Column Form
5 of 7
Footing Excavation and Rebar Placement
6 of 7
Footing Excavation and Rebar Placement
7 of 7
Waterline Excavation
1
of
7
Foundation Work
1 of 7
New Cafeteria-Overall Site
2 of 7
Dock Sump Power and Pump Line
3 of 7
Electrical Slab Rough-In
4 of 7
Slab Edge Forming and Column Form
5 of 7
Footing Excavation and Rebar Placement
6 of 7
Footing Excavation and Rebar Placement
7 of 7
Waterline Excavation
1
of
7
A New Cafeteria (CAF) Video Release
May 2020 Update
Rapid Progress of the New Dining Center Project
1 of 6
Overall Site
2 of 6
Concrete Placed at Dock Walls
3 of 6
Elevator Pit Backfill
4 of 6
Footing Rebar Placement
5 of 6
Electrical Trenching
6 of 6
Cafeteria Dumpster Concrete Enclosure
1
of
6
Rapid Progress of the New Dining Center Project
1 of 6
Overall Site
2 of 6
Concrete Placed at Dock Walls
3 of 6
Elevator Pit Backfill
4 of 6
Footing Rebar Placement
5 of 6
Electrical Trenching
6 of 6
Cafeteria Dumpster Concrete Enclosure
1
of
6
April 2020 Update
A crane will be utilized starting April 11th at the project site to install a grease interceptor. Delivery of the crane will be on April 4 and a trailer will be parked in the front parking lot starting that day until approximately one week later on April 18.
March 2020 Update:
Detour Suggestions
1 of 3
Jacobsen sidewalk removal picture from CAC_3.4.2020_LI (2).jpg
2 of 3
Jacobsen sidewalk removal picture_3.4.2020.jpg
3 of 3
sidewalk closure by pool III_3.4.2020_LI.jpg
1
of
3
Detour Suggestions
1 of 3
Jacobsen sidewalk removal picture from CAC_3.4.2020_LI (2).jpg
2 of 3
Jacobsen sidewalk removal picture_3.4.2020.jpg
3 of 3
sidewalk closure by pool III_3.4.2020_LI.jpg
1
of
3
The cafeteria construction site has removed a part of the sidewalk near the McKay Pool in order to access electrical box and communication wiring for the project.
Please walk closer to the building and around blocked off construction area as shown by the arrow.
Sidewalk will be reinstalled on Friday, March 13.
Please be cautious when walking on the plywood provided to keep the area from becoming muddy.
Jacobsen Construction has prepared sites for demolition and construction for the new cafeteria. During this process, safety is the top priority. Please be aware these sites are temporary. There is no pedestrian traffic along with the Academic Oval by the construction site. Pedestrians are asked to use the walkway by the tennis courts between the McKay Gymnasium & Pool to Hale 1.
February 2020 Update:
Cafeteria Construction Work During February 2020
1 of 4
The Cafeteria Upper Section
2 of 4
Construction Area of the New Cafeteria
3 of 4
Construction Area of the New Cafeteria 2
4 of 4
Side View of the Old Cafeteria Building
1
of
4
Cafeteria Construction Work During February 2020
1 of 4
The Cafeteria Upper Section
2 of 4
Construction Area of the New Cafeteria
3 of 4
Construction Area of the New Cafeteria 2
4 of 4
Side View of the Old Cafeteria Building
1
of
4
January 2020 Update:
Demolition permit has been issued
Interior demolition has begun on a portion of the building
Sidewalks have been removed
Concrete from sidewalks will be crushed and used as structural fill in New Science Building
Completion is expected 3rd quarter of 2021
December 2019 Update:
1 of 2
Cafeteria trenches (2).PNG
2 of 2
Cafeteria project
1
of
2
1 of 2
Cafeteria trenches (2).PNG
2 of 2
Cafeteria project
1
of
2
The design is complete for the new cafeteria project. Phased demolition is projected to start in Fall 2019 to prepare for new construction to follow. The project is scheduled to be completed at the end of 2021.