Help
myBYUH

CURRENT PROJECTS


ORANGE CONE NEWSLETTER – PAINTING PROJECTS click here

 

GROUND WORK

There will be contractors here starting Monday, July 30 for 2 months working on our grounds.  They will start at the front entrance and work around campus.  We appreciate your kokua. 

 

POOL REMODEL

A significant pool remodel is underway which will provide much needed enhancements!   When completed the pool will be beautifully tiled in lieu of the less durable plaster finish and have upgraded filtering and water purification systems.  The pool remodel began May 1, 2018 and is progressing on schedule with an anticipated completion by early September 2018.  Aquatic Solutions Hawaii LLC is the selected contractor performing the work.

We value your safety, please be cautious around the areas that are fenced and be aware of equipment and truck traffic.  Construction activities will be significant during demolition and reconstruction activities. 

Thank you for your patience during the construction process.

See Pool Remodel progress here

 

 

MCKAY AUDITORIUM IMPROVEMENTS

The McKay Auditorium is receiving significant improvements this summer.  Staff at Campus Planning and Construction have been coordinating the work with the talented Dr. Daniel Bradshaw, Chair of the Department of Music and Theatre.  Okland Construction has been retained as the contractor to complete the work.  Work began the week of July 9th with the removal of the old seats.  New upgraded seating has been ordered and will be installed by early September.  This important performing space will also receive a fresh coat of paint along with new aisle and lobby carpet as part of this project.  Thank you for your patience during these improvements.

See McKay Auditorium Improvements here

 

 

OFF-CAMPUS UNIVERSITY HOUSING

A total of 6 duplexes were completed in Fall 2017.  6 more duplexes are currently being built on Moana Street.  The duplexes are in various stages of construction and will be completed throughout Summer and Fall 2018.  The first unit will be turned over the end of July and the last one will be available on or before October 1st.  All duplexes are built to an elevation above flood zone.

See Off- Campus University Housing here

 

 

NA HALE KUMU REMODEL OF TOWNHOMES 9-11

Demolition of the interior finishes and cabinets of 9-11 started on April 9th, beginning first with the tenting for fumigation before the demo.  The tenting is now finished and the remodel is in process.