Seasider Turf Field

March 23, 2021 Update

An aerial side view of the Seasider Turf Field. The field, fencing, and lights are complete. Trees are planted in the seating area which is among the field, GYM Parking, and Napela Drive.

February 17, 2021 Update

January 12, 2021 Update

December 15, 2020 Update

December 8, 2020 Update

December 1, 2020 Update

November 21, 2020 Update

Seasider Sports Field Video

The new field will be raised in elevation to allow subsurface stormwater detention, be covered in durable artificial turf, and receive high-quality sports lighting.

The new light towers will be taller than the existing structures which will allow for better light distribution and highly efficient cut-offs to eliminate light bleed to adjacent areas.

The field will also be striped to accommodate multiple activities as well as allow two half-field games to occur simultaneously.

This improvement is a part of the overall upgrade of the McKay Gymnasium complex.
The upgrade of this field in conjunction with the McKay Pool replacement and Racquetball Court remodel representing a significant investment in the health and well-being of the BYU–Hawaii ohana.

One that will create an all-weather facility that will improve both academic intramural programs for years to come.

Aerial drawn view of a Seasider Sports Field for outdoor sports. The field is highlighted. McKay Gymnasium & Pool and Racquetball Courts are on the right-hand side of the map. A parking lot is in the top middle of the image. The turf field is right below the parking. Also, the paved roads are on the right-hand side and the bottom of the map.
The Map of Turf Field