With a projected completion date in fall 2021, TVA building A1 has an anticipated move-in date for 2022. This building contains 28 units of three varying layouts. This will be the first of several buildings built as part of the Temple View Apartments for married student couples.
Images and Map
1 of 3
Image of New Temple View Apartment #1
2 of 3
Image of New Temple View Apartment #2
3 of 3
The Master Plan of New Temple View Apartments
1
of
3
Images and Map
1 of 3
Image of New Temple View Apartment #1
2 of 3
Image of New Temple View Apartment #2
3 of 3
The Master Plan of New Temple View Apartments
1
of
3
TVA A1 Completed
Building A1, part of phase one for the new TVA housing project, finished construction in February 2022. On March 2, 2022, an open house was held for students, faculty, and the local community members to walk through the new building. Residents are expected to move in during spring 2022.
A1 Exterior
A1 Finished Exterior
1 of 4
TVA A1 Building Exterior
2 of 4
Third Floor Exterior
3 of 4
TVA A1 Second Floor Balcony
4 of 4
TVA Exterior Walkway
1
of
4
A1 Finished Exterior
1 of 4
TVA A1 Building Exterior
2 of 4
Third Floor Exterior
3 of 4
TVA A1 Second Floor Balcony
4 of 4
TVA Exterior Walkway
1
of
4
A1 Interior
A1 Interior
1 of 4
TVA A1 Inside Finished
2 of 4
TVA A1 Interior
3 of 4
TVA A1 Bedroom
4 of 4
TVA A1 Finished Inside Lower Unit
1
of
4
A1 Interior
1 of 4
TVA A1 Inside Finished
2 of 4
TVA A1 Interior
3 of 4
TVA A1 Bedroom
4 of 4
TVA A1 Finished Inside Lower Unit
1
of
4
February 27, 2022 Update
2.27 Updated
1 of 3
02.27 A1
2 of 3
02.27 TVA D3
3 of 3
02.27 TVA D2 Exterior & Pavilions
1
of
3
2.27 Updated
1 of 3
02.27 A1
2 of 3
02.27 TVA D3
3 of 3
02.27 TVA D2 Exterior & Pavilions
1
of
3
February 6, 2022 Update
02.06 Updates
1 of 3
02.06 A1 Exterior
2 of 3
02.06 D2 & Pavilions
3 of 3
02.06 Pavilion Slabs & Columns
1
of
3
02.06 Updates
1 of 3
02.06 A1 Exterior
2 of 3
02.06 D2 & Pavilions
3 of 3
02.06 Pavilion Slabs & Columns
1
of
3
December 12, 2021 Update
12.12 Updates
1 of 3
TVA A1 Exterior 12.12
2 of 3
D2 Exterior and Pavilion Footings 12.12
3 of 3
D3 12.12
1
of
3
12.12 Updates
1 of 3
TVA A1 Exterior 12.12
2 of 3
D2 Exterior and Pavilion Footings 12.12
3 of 3
D3 12.12
1
of
3
November 14, 2021 Update
Updates on 11.14
1 of 3
D3 work 11.14
2 of 3
A1 Front 11.14
3 of 3
A1 Back 11.14
1
of
3
Updates on 11.14
1 of 3
D3 work 11.14
2 of 3
A1 Front 11.14
3 of 3
A1 Back 11.14
1
of
3
November 7, 2021 Update
Updates to Exterior
1 of 4
A1 Awnings 11.7
2 of 4
A1 Exterior 11.7
3 of 4
D2 Exterior 11.7
4 of 4
D3 Exterior 11.7
1
of
4
Updates to Exterior
1 of 4
A1 Awnings 11.7
2 of 4
A1 Exterior 11.7
3 of 4
D2 Exterior 11.7
4 of 4
D3 Exterior 11.7
1
of
4
October 31, 2021 Update
New Updates
1 of 4
A1 Kitchen 10.31
2 of 4
A1 Exterior 10.31
3 of 4
D3 TVA 10.31
4 of 4
A1 Parking Lot 10.31
1
of
4
New Updates
1 of 4
A1 Kitchen 10.31
2 of 4
A1 Exterior 10.31
3 of 4
D3 TVA 10.31
4 of 4
A1 Parking Lot 10.31
1
of
4
September 26, 2021 Update
Updates to Exterior & Interior
1 of 3
A1 Inside Interior Apartment
2 of 3
D2 Crane Work
3 of 3
A1 Parking Lot Prep 9.26
1
of
3
Updates to Exterior & Interior
1 of 3
A1 Inside Interior Apartment
2 of 3
D2 Crane Work
3 of 3
A1 Parking Lot Prep 9.26
1
of
3
September 5, 2021 Update
A1 Updates
1 of 3
A1 Back Exterior View
2 of 3
A1 Interior
3 of 3
TVA A1 Interior Paint
1
of
3
A1 Updates
1 of 3
A1 Back Exterior View
2 of 3
A1 Interior
3 of 3
TVA A1 Interior Paint
1
of
3
August 27, 2021 Update
Exterior Views of the new TVA Complexes
1 of 2
Aerial view of the D2 Complex
2 of 2
View of D3 Foundation
1
of
2
Exterior Views of the new TVA Complexes
1 of 2
Aerial view of the D2 Complex
2 of 2
View of D3 Foundation
1
of
2
August 20, 2021 Update
Exterior Work Progress
1 of 4
Second Floor Drywall
2 of 4
Wainscoat and Landscaping
3 of 4
Main Sensor
4 of 4
Floor Pad
1
of
4
Exterior Work Progress
1 of 4
Second Floor Drywall
2 of 4
Wainscoat and Landscaping
3 of 4
Main Sensor
4 of 4
Floor Pad
1
of
4
August 8, 2021 Update
Farther Progress on Walls
1 of 3
ICF Blocks
2 of 3
Foundation Walls
3 of 3
Drywall: Floors 2 and 3
1
of
3
Farther Progress on Walls
1 of 3
ICF Blocks
2 of 3
Foundation Walls
3 of 3
Drywall: Floors 2 and 3
1
of
3
August 4, 2021 Update
New TVA Buildings' Exterior Progress
1 of 3
TVA Building A1: Exterior Progress
2 of 3
TVA Building D2: Wall Progress
3 of 3
TVA Building D3: Foundation Walls
1
of
3
New TVA Buildings' Exterior Progress
1 of 3
TVA Building A1: Exterior Progress
2 of 3
TVA Building D2: Wall Progress
3 of 3
TVA Building D3: Foundation Walls
1
of
3
July 28, 2021 Update
Exterior Updates
1 of 5
Exterior Siding
2 of 5
Asphalt Roof
3 of 5
Columns
4 of 5
Floor Joist
5 of 5
Foundation Wall Forms
1
of
5
Exterior Updates
1 of 5
Exterior Siding
2 of 5
Asphalt Roof
3 of 5
Columns
4 of 5
Floor Joist
5 of 5
Foundation Wall Forms
1
of
5
July 20, 2021 Update
Window Installation and Poured Slab of Concrete
1 of 4
Overall Update Photo
2 of 4
Exterior Siding
3 of 4
Structure and Elevator Shaft
4 of 4
Poured Slab
1
of
4
Window Installation and Poured Slab of Concrete
1 of 4
Overall Update Photo
2 of 4
Exterior Siding
3 of 4
Structure and Elevator Shaft
4 of 4
Poured Slab
1
of
4
July 13, 2021 Update
Shingles, ICF, and Concrete Work
1 of 4
Shingles
2 of 4
Shingles and Siding
3 of 4
ICF Walls
4 of 4
Preparation for Concrete Pouring
1
of
4
Shingles, ICF, and Concrete Work
1 of 4
Shingles
2 of 4
Shingles and Siding
3 of 4
ICF Walls
4 of 4
Preparation for Concrete Pouring
1
of
4
July 7, 2021 Update
New Updates
1 of 4
Shingles and Plumbing
2 of 4
Shingles and Electrical
3 of 4
Stairs and Elevator Shaft
4 of 4
Fabric and Rebar
1
of
4
New Updates
1 of 4
Shingles and Plumbing
2 of 4
Shingles and Electrical
3 of 4
Stairs and Elevator Shaft
4 of 4
Fabric and Rebar
1
of
4
June 29, 2021 Update
TVA Building A1, D2, and D3: Exterior Work
1 of 4
TVA Building A1: Exterior Work #1
2 of 4
TVA Building A1: Exterior Work #2
3 of 4
TVA Building D2: Level 1
4 of 4
TVA Building D3: Exterior Work
1
of
4
TVA Building A1, D2, and D3: Exterior Work
1 of 4
TVA Building A1: Exterior Work #1
2 of 4
TVA Building A1: Exterior Work #2
3 of 4
TVA Building D2: Level 1
4 of 4
TVA Building D3: Exterior Work
1
of
4
June 21, 2021 Update
Progression
1 of 3
TVA Building A1: Roof Trusses
2 of 3
TVA Building D2: Level 1 Walls
3 of 3
TVA Building D3: Base
1
of
3
Progression
1 of 3
TVA Building A1: Roof Trusses
2 of 3
TVA Building D2: Level 1 Walls
3 of 3
TVA Building D3: Base
1
of
3
June 11, 2021 Update
New TVA Buildings: Work Progress
1 of 3
TVA Building A1: Trusses
2 of 3
TVA Building D2: Steel Structure
3 of 3
Another Layer of Gravel
1
of
3
New TVA Buildings: Work Progress
1 of 3
TVA Building A1: Trusses
2 of 3
TVA Building D2: Steel Structure
3 of 3
Another Layer of Gravel
1
of
3
June 1, 2021 Update
New TVA Buildings: More Updates
1 of 3
Preparing Mat Footing
2 of 3
Floor Slab
3 of 3
Third Level Walls
1
of
3
New TVA Buildings: More Updates
1 of 3
Preparing Mat Footing
2 of 3
Floor Slab
3 of 3
Third Level Walls
1
of
3
May 21, 2021 Update
New Updates
1 of 3
TVA Building A1: New Update
2 of 3
TVA Building D2: New Update
3 of 3
TVA Building D3: New Update
1
of
3
New Updates
1 of 3
TVA Building A1: New Update
2 of 3
TVA Building D2: New Update
3 of 3
TVA Building D3: New Update
1
of
3
May 11, 2021 Update
TVA Buildings A1, D2, and D3: New Updates
1 of 4
The Floor of Third Level
2 of 4
TVA Building A1: The Floor of Third Level
3 of 4
Excavation and Leveling
4 of 4
Concrete Placement in Process
1
of
4
TVA Buildings A1, D2, and D3: New Updates
1 of 4
The Floor of Third Level
2 of 4
TVA Building A1: The Floor of Third Level
3 of 4
Excavation and Leveling
4 of 4
Concrete Placement in Process
1
of
4
May 4, 2021 Update
Update: A1 and D2
1 of 3
TVA Building D2: Concrete Layer
2 of 3
TVA Building A1 Update Photo
3 of 3
TVA Building A1: Aerial shot
1
of
3
Update: A1 and D2
1 of 3
TVA Building D2: Concrete Layer
2 of 3
TVA Building A1 Update Photo
3 of 3
TVA Building A1: Aerial shot
1
of
3
April 28, 2021 Update
New TVA Building: Update
1 of 2
TVA Building D2: Slab Preparation
2 of 2
TVA Building A1: Second Floor
1
of
2
New TVA Building: Update
1 of 2
TVA Building D2: Slab Preparation
2 of 2
TVA Building A1: Second Floor
1
of
2
April 20, 2021 Update
Progress of A1, D2, and D3
1 of 3
TVA Building A1: ICF Walls
2 of 3
Termite Barrier
3 of 3
TVA Building D3: Excavation
1
of
3
Progress of A1, D2, and D3
1 of 3
TVA Building A1: ICF Walls
2 of 3
Termite Barrier
3 of 3
TVA Building D3: Excavation
1
of
3
April 12, 2021 Update
ICF Walls and Termite Barrier
1 of 7
ICF Walls #1
2 of 7
ICF Walls #2
3 of 7
Termite Barrier
4 of 7
ICF and Steel Columns
5 of 7
TVA Building A1: Interior Framing Started
6 of 7
TVA Building D2: Preparing Slab for Placement
7 of 7
TVA Building A1: Barrier and Rebar
1
of
7
ICF Walls and Termite Barrier
1 of 7
ICF Walls #1
2 of 7
ICF Walls #2
3 of 7
Termite Barrier
4 of 7
ICF and Steel Columns
5 of 7
TVA Building A1: Interior Framing Started
6 of 7
TVA Building D2: Preparing Slab for Placement
7 of 7
TVA Building A1: Barrier and Rebar
1
of
7
April 2, 2021 Update
TVA Buildings A1, D2, and D3
1 of 5
TVA Building A1: ICF Walls
2 of 5
ICF Walls
3 of 5
Preparing the Mat Slap
4 of 5
Excavation #1
5 of 5
Excavation #2
1
of
5
TVA Buildings A1, D2, and D3
1 of 5
TVA Building A1: ICF Walls
2 of 5
ICF Walls
3 of 5
Preparing the Mat Slap
4 of 5
Excavation #1
5 of 5
Excavation #2
1
of
5
March 30, 2021 Update
Buildings A1, D2, and D3
1 of 3
New TVA Building D3
2 of 3
Building D2: Elevator Pit Finished
3 of 3
TVA Building A1: Pouring Concrete Slab
1
of
3
Buildings A1, D2, and D3
1 of 3
New TVA Building D3
2 of 3
Building D2: Elevator Pit Finished
3 of 3
TVA Building A1: Pouring Concrete Slab
1
of
3
March 22, 2021 Update
TVA Buildings A1 and D2: Overall
1 of 2
TVA Building A1: Slab Placement
2 of 2
TVA Building D2: Overall
1
of
2
TVA Buildings A1 and D2: Overall
1 of 2
TVA Building A1: Slab Placement
2 of 2
TVA Building D2: Overall
1
of
2
March 15, 2021 Update
New TVA Building A1 and D2 Progress
1 of 3
TVA Building A1: Gravel placed on the mat slab
2 of 3
TVA D2: Elevator Pit
3 of 3
New TVA Building D2: Plumbing Backfilled
1
of
3
New TVA Building A1 and D2 Progress
1 of 3
TVA Building A1: Gravel placed on the mat slab
2 of 3
TVA D2: Elevator Pit
3 of 3
New TVA Building D2: Plumbing Backfilled
1
of
3
March 8, 2021 Update
A1 and D2
1 of 3
New TVA Building A1: Aerial Shot
2 of 3
Building A1: Aerial
3 of 3
Building D2: Aerial
1
of
3
A1 and D2
1 of 3
New TVA Building A1: Aerial Shot
2 of 3
Building A1: Aerial
3 of 3
Building D2: Aerial
1
of
3
March 1, 2021 Update
TVA Building A1 and D2
1 of 3
TVA Building A1: Mat Slab Prep
2 of 3
TVA Building D2: Plumbing
3 of 3
TVA Building D2: Plumbing Excavation
1
of
3
TVA Building A1 and D2
1 of 3
TVA Building A1: Mat Slab Prep
2 of 3
TVA Building D2: Plumbing
3 of 3
TVA Building D2: Plumbing Excavation
1
of
3
February 22, 2021 Update
TVA Building A1 and D2 Overall
1 of 3
TVA Building A1: Overall
2 of 3
TVA Building D2: Plumbing Excavation
3 of 3
TVA Building D2: Overall
1
of
3
TVA Building A1 and D2 Overall
1 of 3
TVA Building A1: Overall
2 of 3
TVA Building D2: Plumbing Excavation
3 of 3
TVA Building D2: Overall
1
of
3
February 15, 2021 Update
February 5, 2021 Update
Elevator Wood Forms
1 of 3
TVA A1: Wooden Form #1
2 of 3
TVA A1: Wooden Form #2
3 of 3
TVA D2: Leveling
1
of
3
Elevator Wood Forms
1 of 3
TVA A1: Wooden Form #1
2 of 3
TVA A1: Wooden Form #2
3 of 3
TVA D2: Leveling
1
of
3
February 2, 2021 Update
Rerouting Electrical
1 of 3
TVA D2: Rerouting Electrical #1
2 of 3
TVA D2: Rerouting Electrical #2
3 of 3
TVA A1 Elevator: Wooden Form
1
of
3
Rerouting Electrical
1 of 3
TVA D2: Rerouting Electrical #1
2 of 3
TVA D2: Rerouting Electrical #2
3 of 3
TVA A1 Elevator: Wooden Form
1
of
3
January 26, 2021 Update
January 18, 2021 Update
TVA Building A1
1 of 2
Elevator Excavation
2 of 2
Elevator Pit
1
of
2
TVA Building A1
1 of 2
Elevator Excavation
2 of 2
Elevator Pit
1
of
2
January 8, 2021 Update
Steel Columns
1 of 2
New TVA Building: Leveling
2 of 2
New TVA Building: Overall Site
1
of
2
Steel Columns
1 of 2
New TVA Building: Leveling
2 of 2
New TVA Building: Overall Site
1
of
2
November 23, 2020 Update
BYUH TVA Housing
1 of 3
TVA Bldg A1-Plumbing excavation and Installation
2 of 3
Dog Leg Parking: Curbs Placed
3 of 3
HGB Parking Lot: Excavation Ongoing
1
of
3
BYUH TVA Housing
1 of 3
TVA Bldg A1-Plumbing excavation and Installation
2 of 3
Dog Leg Parking: Curbs Placed
3 of 3
HGB Parking Lot: Excavation Ongoing
1
of
3
November 9, 2020 Update
1 of 2
Screen Shot 2020-11-19 at 10.38.38 AM.png
2 of 2
Screen Shot 2020-11-19 at 10.38.55 AM.png
1
of
2
1 of 2
Screen Shot 2020-11-19 at 10.38.38 AM.png
2 of 2
Screen Shot 2020-11-19 at 10.38.55 AM.png
1
of
2
Fencing for new TVA Construction
Fencing for the new TVA apartment construction site will be adjusted to include the areas needed for parking, utility relocation, and pavilion demolition this week. Please see the picture.
New Temple View Apartment
The Temple View Apartment area will be updated and densified with the addition of several new three-story structures. The project will be constructed in two phases. The first phase will include three structures that will be constructed along the southern edge of the community. The second phase will include six structures with associated parking and site infrastructure. The buildings will be constructed of insulated concrete forms (ICF) that will overcome many of the challenges of the existing construction. The first phase of construction will begin as soon as building permits are approved and will last about two years. The second phase will begin following phase one and will take about three years to complete.